Cavendish House
Cavendish House 105-109 High Street, Colliers Wood, London, SW19 2HR
Client – Rocco Homes Ltd
Consultant – Ian White Associates Ltd
Duration – 12 months
-HV/LV Substation
-Substation earthing
-Generator installation & automatic transfer switches
-Landlords fully integrated services
-LV Mains Distribution to 55no apartments
-BT DP & Fibre Optic Installation
-Plant & Mechanical supplies
-Modular lighting system
-LV Mains Distribution to landlords panels and boards